Status: Delivered
Property type is Villa
Estimated completion time is 12 working days
Project Timeline
-
20-Oct-2025
✅ Project Delivered
-
20-Oct-2025
Project Booked
-
21-Oct-2025
Work Started
-
21-Oct-2025
Surface cleaning & wall paint started
-
22-Oct-2025
Wall paint completed
-
23-Oct-2025
Wallpaper installation in process
-
25-Oct-2025
Installation in Progress
-
05-Nov-2025
Delivery scheduled for TV Unit on 07-11-2025
-
07-Nov-2025
Installation Completed
Project Details
- Paint work
- Wallpaper for Master Room
- Wallpaper for Maria Room
- Wallpaper for Muhammad Room
- TV Wall Unit
0
Discussions
No discussion started yet. Be the first to start one, share your ideas, suggestions, or questions. We would love to hear from you and respond.
More Projects Completed by Instylea
- Project: 001007 CompletedAjman VillaFurniture upholstery, Carpet Installation and installation of curtains
- Project: 001008 CompletedAbu Dhabi ApartmentBlackout and Sheer curtains for the rooms
- Project: 001009 CompletedSharjah VillaWavy Blackout and Sheer curtains for the Villa rooms and halls
- Project: 001010 CompletedDubai ApartmentBlackout and Sheer curtains for the rooms
- Project: 001011 CompletedAl Taawun Dubai ApartmentInstallation of Wavy Curtains for the windows
- Project: 001012 CompletedDubai ApartmentInstallation of Roman Blinds for the windows