Status: Delivered
Property type is Villa
Estimated completion time is 15 working days
Project Timeline
-
29-Nov-2025
✅ Project Delivered
-
29-Nov-2025
Project Booked
-
30-Nov-2025
Material assigned to carpentry
-
01-Dec-2025
Process hold due to holiday
-
08-Dec-2025
Cutting & Processing Started
-
10-Dec-2025
Material / Hardware assembling completed
-
12-Dec-2025
Finishing process
-
13-Dec-2025
Quality inspection complete
-
13-Dec-2025
Delivery Scheduled
-
14-Dec-2025
Delivery is temporarily on hold due to weather conditions.
-
14-Dec-2025
Out for Delivery
-
14-Dec-2025
Installation Scheduled
-
14-Dec-2025
Installation in Progress
-
15-Dec-2025
Installation Continued
-
15-Dec-2025
Installation Completed
Project Details
- Tv wall unit with LED
0
Discussions
No discussion started yet. Be the first to start one, share your ideas, suggestions, or questions. We would love to hear from you and respond.
More Projects Completed by Instylea
- Project: 001007 CompletedAjman VillaFurniture upholstery, Carpet Installation and installation of curtains
- Project: 001008 CompletedAbu Dhabi ApartmentBlackout and Sheer curtains for the rooms
- Project: 001009 CompletedSharjah VillaWavy Blackout and Sheer curtains for the Villa rooms and halls
- Project: 001010 CompletedDubai ApartmentBlackout and Sheer curtains for the rooms
- Project: 001011 CompletedAl Taawun Dubai ApartmentInstallation of Wavy Curtains for the windows
- Project: 001012 CompletedDubai ApartmentInstallation of Roman Blinds for the windows