Status: The work is currently ongoing.
Property type is Villa
Estimated completion time is 12 working days
Project Timeline
-
Loading...
Next update in progress
-
February 26, 2026
Waiting for polishing and textures to be dried.
-
February 25, 2026
Polishing & Finishing in Progress
-
February 22, 2026
Metal / Hardware Work in Progress
-
February 20, 2026
Cutting & Processing Started
-
February 11, 2026
Work Started
-
February 9, 2026
Project design aproved
-
February 1, 2026
Project 2D and 3D in process
-
January 21, 2026
Material selection approved
-
January 14, 2026
Project Booked
Project Details
- Wooden cladding with led and tv console with bottom led
More Projects Completed by Instylea
- Project: 001007 CompletedAjman VillaFurniture upholstery, Carpet Installation and installation of curtains
- Project: 001008 CompletedAbu Dhabi ApartmentBlackout and Sheer curtains for the rooms
- Project: 001009 CompletedSharjah VillaWavy Blackout and Sheer curtains for the Villa rooms and halls
- Project: 001010 CompletedDubai ApartmentBlackout and Sheer curtains for the rooms
- Project: 001011 CompletedAl Taawun Dubai ApartmentInstallation of Wavy Curtains for the windows
- Project: 001012 CompletedDubai ApartmentInstallation of Roman Blinds for the windows